A potential change order (PCO) can be an item that is expected to result in extra work, or additional costs. A PCO can also result from owner directives, bulletins, clarifications or changes to the original plans. Any of these changes might require a change.
The Potential Change Orders form is the starting point of the change order process. Use the PCO form to track possible and actual changes, the impact of the change on the budget and the cost, as well as which companies are affected by the change. As a PCO moves from being a possible cost to being part of a change order, update and modify the impact of the change in the Potential Change Orders form.
To create a potential change order
The Potential Change Order form appears.
*This field is required.
—Or—
To save the changes and close the form, click > Save and Exit.