Contract Invoices

Use the Contract Invoices form to record invoices you have received from subcontractors, and to determine the value of the progress payment to the subcontractor. You can create a contract invoice for any contract that commits costs in the budget.

If this is the second or greater invoice you are creating for a contract, values of previously performed work and installed material are displayed on the Detailed Items tab. Prolog Converge calculates the Previous Work Material Install Value for the current invoice by adding together the values in the Work this Invoice Value, Material Install This Invoice Value, and Previous Work Material Install Value columns from the previous invoice.

To create a contract

  1. On the View menu, click Cost Control > Contract Invoices, and then select a view.
  2. Click .
  3. The Contract Invoices form appears.

  4. In the Creating dialog box, select the contract for which you want to create a contract invoice, and then click Create.
  5. Enter or view the following information:
  6. *This field is required.

  7. To save the changes and keep the form open, click > Save.
  8. —Or—

    To save the changes and close the form, click > Save and Exit.